List of necessary instructions in the boiler room. Duties of boiler room attendants

APPROVE ____________________________________ (name of the position of the head of the enterprise) ____________________________________ (Full name, signature) "____" _____________________ _____ Mr. M.P.

REGULATIONS on the boiler plant of the company

1. GENERAL PROVISIONS

1.1. The boiler house is a structural subdivision of the enterprise. The employees of the boiler room report directly to ________________________.

1.2. The boiler-house was created on the basis of the order of the head of the enterprise N ____ from "___" ___________.

1.3. The head of the boiler house is appointed and dismissed by the order of the head of the enterprise.

The employees of the boiler house are appointed and dismissed by the order of the head of the enterprise on the recommendation of the Head of the boiler house.

1.4. The boiler house in its work is guided by:

The Constitution Russian Federation;

Federal laws of the Russian Federation;

Decrees and orders of the President of the Russian Federation;

Decrees and orders of the Government of the Russian Federation;

Laws of ________________ (specify subject of the Russian Federation);

The Articles of Association of the enterprise;

Local acts of the enterprise;

The present Regulations.

1.5. The boiler house should have documents and materials on the following issues:

Decrees, orders, orders, other governing and regulatory documents of higher authorities concerning the heat supply of consumers, safe work  boiler equipment, organization of production and economic activities of the boiler house;

Rules of technical operation of electric and thermal stations and networks;

Technical characteristics of the boiler house equipment;

Technological process of generation of heat energy and heat supply to consumers;

Electrical and technological diagrams of the boiler room;

Schemes of heat, steam and water pipes and external heating systems;

Fuel supply schemes, schematic diagrams  and the principles of the operation of relay protection, automatic and regulating devices, instrumentation, signaling and communication equipment;

Environmental protection requirements;

Safety regulations;

General information on the organization of work with personnel engaged in energy production;

Provisions and instructions for the investigation and recording of industrial accidents, violations in the operation of heat networks, power systems and power connections;

Methods of effective use of office equipment and other technical means of managerial work;

Rules of internal labor regulations; rules and norms of labor protection.

2. STRUCTURE OF BOILER

2.1. The structure and staff of the boiler room is approved by the head of the enterprise.

2.2. The boiler room is managed by the Head of the boiler room.

2.3. The staff of the boiler room includes (specify the positions):

- __________________________________________;

- __________________________________________;

- __________________________________________;

- __________________________________________.

3. MAIN OBJECTIVES OF BOILER

3.1. Provision of uninterrupted heat supply to consumers in accordance with the approved schedule.

3.2. Ensuring the safe operation of equipment.

3.3. Rational use of fuel and energy resources.

4. BOILER FUNCTIONS

In accordance with the tasks assigned to it, the boiler-house performs the following functions:

4.1. Uninterrupted heat supply to consumers in accordance with the approved schedule.

4.2. Ensuring the safe operation of equipment, compliance with the requirements of the rules of technical operation, the rules of labor protection and fire safety.

4.3. Development and implementation of organizational and technical measures to improve the reliability of boiler equipment, reduce heat losses.

4.4. Rational use of fuel and energy resources, reduction of downtime of equipment during the repair period, preparation for seasonal conditions.

4.5. Conducting a comprehensive scientific examination of technical tasks for the most important research projects, projects, concepts, analytical and other documents on technical, organizational, economic, legal and other issues, as well as preparing reports on the results of the examination of the company's management.

4.6. Conducting experimental works and testing new equipment before putting it into operation.

4.7. Acceptance of equipment after major repairs  and mounting.

4.8. Study of the causes of failures in the operation of boiler equipment, accidents, cases of industrial injuries.

4.9. Development of new regulatory documents, drawing up applications for tools, materials, spare parts, protective equipment necessary for maintenance and repair of boiler equipment.

4.10. Rational use of material values.

4.11. Accounting and analysis of equipment operation.

4.12. Timely reporting on the results of the boiler plant.

4.13. Improving the qualification of boiler room personnel.

4.14. Carrying out anti-fire and fire fighting personnel training.

4.15. Implementation of the organization of reference and reference information relating to the functions of the boiler house.

4.16. Implementation in accordance with the legislation of the Russian Federation of the acquisition, storage, accounting and use of archival documents formed during the activities of the boiler house.

The imposition on the boiler house of functions not related to records management is not allowed.

4.17. Boiler House employees within the scope of their competence to resolve the tasks assigned to the boiler house have the right:

4.18. Request in due order from the structural units of the company information (materials) on issues within the competence of the boiler house.

4.19. Check the readings of the instruments that record the results production activities  Boiler house and located on the territory of the structural units of the enterprise.

4.20. Conduct negotiations with outside organizations within its competence in accordance with the established procedure, and sign agreements.

4.21. Use the funds allocated to finance the boiler house for the purchase of equipment, components, tools, repair equipment.

4.22. Make proposals on issues within the competence of the boiler house.

5. INTERACTION WITH THE STRUCTURAL DIVISIONS OF THE ENTERPRISE

5.1. In the process of production activities of the enterprise, the boiler house interacts with the following structural subdivisions:

- ________________________________________________________,

- ________________________________________________________,

- ________________________________________________________.

6. RESPONSIBILITY

6.1. All responsibility for the quality and timeliness of the performance of the tasks and functions assigned to these Boilers is borne by the Head of the boiler house.

6.2. Responsibility of the boiler house workers is established by the current legislation and job descriptions.

6.3. The head and other employees of the boiler house are personally responsible for the compliance of the documents and correspondent transactions with the legislation of the Russian Federation with them.

7. CRITERIA FOR ESTIMATION OF THE ACTIVITY OF BOILER

7.1. Timely and high-quality implementation of set goals and objectives.

7.2. Qualitative performance of functional duties.

Head of the Boiler Room: _____________________________ / __________________ / (signature) (Full name) This Regulation is familiar to (a) _________________ / __________________ /

APPROVE ___________________________________ (name of the head of the enterprise)

  ___________________________________ (Full name, signature)

  "____" _____________________ ____

POSITION

about the boiler plant

1. GENERAL PROVISIONS

1.1. The boiler house is a structural subdivision of the enterprise. The employees of the boiler room report directly to __________________________________.

1.2. The boiler-house was created on the basis of the order of the head of the enterprise N ____ from "__" ___________.

1.3. The head of the boiler house is appointed and dismissed by the order of the head of the enterprise.

The employees of the boiler house are appointed and dismissed by the order of the head of the enterprise on the proposal of the Head of the boiler house.

1.4. The boiler house in its work is guided by:

The Constitution of the Russian Federation;

Federal laws of the Russian Federation;

Decrees and orders of the President of the Russian Federation;

Decrees and orders of the Government of the Russian Federation;

Laws of ________________ (specify subject of the Russian Federation);

The Articles of Association of the enterprise;

Local acts of the enterprise;

The present position.

1.5. The boiler room should have documents and materials on the following issues:

Decisions, orders, orders, other governing and regulatory documents of higher authorities concerning heat supply to consumers, safe operation of boiler equipment, organization of production and economic activities of the boiler house;

Rules of technical operation of electric and thermal stations and networks;

Technical characteristics of the boiler room equipment;

Technological process of generation of heat energy and heat supply to consumers;

Electrical and technological schemes of the boiler house;

Schemes of heat, steam and water pipes and external heating systems;

Fuel supply schemes, circuit diagrams and operating principles of relay protection, automatic and regulating devices, instrumentation, signaling and communication equipment;

Environmental protection requirements;

Safety regulations;

General information on the organization of work with personnel engaged in energy production;

Provisions and instructions for the investigation and recording of industrial accidents, violations in the operation of heat networks, power systems and power connections;

Methods of effective use of office equipment and other technical means of managerial work;

Rules of internal labor regulations; rules and norms of labor protection.

2. STRUCTURE OF BOILER

2.1. The structure and staff of the boiler room is approved by the head of the enterprise.

2.2. The boiler room is managed by the boiler house manager.

2.3. The staff of the boiler room includes (specify the positions):

- __________________________________________;

- __________________________________________;

- __________________________________________;

- __________________________________________.

3. MAIN OBJECTIVES OF BOILER

3.1. Provision of uninterrupted heat supply to consumers in accordance with the approved schedule.

3.2. Ensuring the safe operation of equipment.

3.3. Rational use of fuel and energy resources.

4. BOILER FUNCTIONS

In accordance with the tasks assigned to it, the boiler-house performs the following functions:

4.1. Uninterrupted heat supply to consumers in accordance with the approved schedule.

4.2. Ensuring the safe operation of equipment, compliance with the requirements of the rules of technical operation, the rules of labor protection and fire safety.

4.3. Development and implementation of organizational and technical measures to improve the reliability of boiler equipment, reduce heat losses.

4.4. Rational use of fuel and energy resources, reduction of downtime of equipment during the repair period, preparation for seasonal conditions.

4.5. Conducting a comprehensive scientific examination of technical tasks for the most important research projects, projects, concepts, analytical and other documents on technical, organizational, economic, legal and other issues, as well as preparing reports on the results of the examination of the company's management.

4.6. Conducting experimental works and testing new equipment before putting it into operation.

4.7. Acceptance of equipment after overhaul and installation.

4.8. Study of the causes of failures in the operation of boiler equipment, accidents, cases of industrial injuries.

4.9. Development of new regulatory documents, drawing up applications for tools, materials, spare parts, protective equipment necessary for maintenance and repair of boiler equipment.

4.10. Rational use of material values.

4.11. Accounting and analysis of equipment operation.

4.12. Timely reporting on the results of the boiler plant.

4.13. Improving the qualification of boiler room personnel.

4.14. Carrying out anti-fire and fire fighting personnel training.

4.15. Implementation of the organization of reference and reference information relating to the functions of the boiler house.

4.16. Implementation in accordance with the legislation of the Russian Federation of the acquisition, storage, accounting and use of archival documents formed during the activities of the boiler house.

The imposition on the boiler house of functions not related to records management is not allowed.

4.17. Boiler House employees within the scope of their competence to resolve the tasks assigned to the boiler house have the right:

4.18. Request in due order from the structural units of the company information (materials) on issues within the competence of the boiler house.

4.19. Check the readings of the devices that record the results of the production activities of the boiler house and located on the territory of the structural divisions of the enterprise.

4.20. Conduct negotiations with outside organizations within its competence in accordance with the established procedure, and sign agreements.

4.21. Use the funds allocated to finance the boiler house for the purchase of equipment, components, tools, repair equipment.

4.22. Make proposals on issues within the competence of the boiler house.

5. INTERACTION WITH THE STRUCTURAL DIVISIONS OF THE ENTERPRISE

5.1. In the process of production activity, the boiler plant cooperates with the following structural subdivisions:

- ______________________________________________________________,

- ______________________________________________________________,

- ______________________________________________________________.

6. RESPONSIBILITY

6.1. All responsibility for the quality and timeliness of the performance of the tasks and functions assigned to these Boilers is borne by the Head of the boiler house.

6.2. Responsibility of the boiler house workers is established by the current legislation and job descriptions.

6.3. The head and other employees of the boiler house are personally responsible for the compliance of the documents and correspondent transactions with the legislation of the Russian Federation with them.

7. CRITERIA FOR ESTIMATION OF THE ACTIVITY OF BOILER

7.1. Timely and high-quality implementation of set goals and objectives.

7.2. Qualitative performance of functional duties.

Head of the Boiler Room: ____________________________ / ________________ / / (signature) (Full name)

APPROVE ___________________________________ (name of the head of the enterprise)

  ___________________________________ (Full name, signature)

  "____" _____________________ ____

POSITION

about the boiler plant

1. GENERAL PROVISIONS

1.1. The boiler house is a structural subdivision of the enterprise. The employees of the boiler room report directly to __________________________________.

1.2. The boiler-house was created on the basis of the order of the head of the enterprise N ____ from "__" ___________.

1.3. The head of the boiler house is appointed and dismissed by the order of the head of the enterprise.

The employees of the boiler house are appointed and dismissed by the order of the head of the enterprise on the proposal of the Head of the boiler house.

1.4. The boiler house in its work is guided by:

The Constitution of the Russian Federation;

Federal laws of the Russian Federation;

Decrees and orders of the President of the Russian Federation;

Decrees and orders of the Government of the Russian Federation;

Laws of ________________ (specify subject of the Russian Federation);

The Articles of Association of the enterprise;

Local acts of the enterprise;

The present position.

1.5. The boiler room should have documents and materials on the following issues:

Decisions, orders, orders, other governing and regulatory documents of higher authorities concerning heat supply to consumers, safe operation of boiler equipment, organization of production and economic activities of the boiler house;

Rules of technical operation of electric and thermal stations and networks;

Technical characteristics of the boiler room equipment;

Technological process of generation of heat energy and heat supply to consumers;

Electrical and technological schemes of the boiler house;

Schemes of heat, steam and water pipes and external heating systems;

Fuel supply schemes, circuit diagrams and operating principles of relay protection, automatic and regulating devices, instrumentation, signaling and communication equipment;

Environmental protection requirements;

Safety regulations;

General information on the organization of work with personnel engaged in energy production;

Provisions and instructions for the investigation and recording of industrial accidents, violations in the operation of heat networks, power systems and power connections;

Methods of effective use of office equipment and other technical means of managerial work;

Rules of internal labor regulations; rules and norms of labor protection.

2. STRUCTURE OF BOILER

2.1. The structure and staff of the boiler room is approved by the head of the enterprise.

2.2. The boiler room is managed by the boiler house manager.

2.3. The staff of the boiler room includes (specify the positions):

- __________________________________________;

- __________________________________________;

- __________________________________________;

- __________________________________________.

3. MAIN OBJECTIVES OF BOILER

3.1. Provision of uninterrupted heat supply to consumers in accordance with the approved schedule.

3.2. Ensuring the safe operation of equipment.

3.3. Rational use of fuel and energy resources.

4. BOILER FUNCTIONS

In accordance with the tasks assigned to it, the boiler-house performs the following functions:

4.1. Uninterrupted heat supply to consumers in accordance with the approved schedule.

4.2. Ensuring the safe operation of equipment, compliance with the requirements of the rules of technical operation, the rules of labor protection and fire safety.

4.3. Development and implementation of organizational and technical measures to improve the reliability of boiler equipment, reduce heat losses.

4.4. Rational use of fuel and energy resources, reduction of downtime of equipment during the repair period, preparation for seasonal conditions.

4.5. Conducting a comprehensive scientific examination of technical tasks for the most important research projects, projects, concepts, analytical and other documents on technical, organizational, economic, legal and other issues, as well as preparing reports on the results of the examination of the company's management.

4.6. Conducting experimental works and testing new equipment before putting it into operation.

4.7. Acceptance of equipment after overhaul and installation.

4.8. Study of the causes of failures in the operation of boiler equipment, accidents, cases of industrial injuries.

4.9. Development of new regulatory documents, drawing up applications for tools, materials, spare parts, protective equipment necessary for maintenance and repair of boiler equipment.

4.10. Rational use of material values.

4.11. Accounting and analysis of equipment operation.

4.12. Timely reporting on the results of the boiler plant.

4.13. Improving the qualification of boiler room personnel.

4.14. Carrying out anti-fire and fire fighting personnel training.

4.15. Implementation of the organization of reference and reference information relating to the functions of the boiler house.

4.16. Implementation in accordance with the legislation of the Russian Federation of the acquisition, storage, accounting and use of archival documents formed during the activities of the boiler house.

The imposition on the boiler house of functions not related to records management is not allowed.

4.17. Boiler House employees within the scope of their competence to resolve the tasks assigned to the boiler house have the right:

4.18. Request in due order from the structural units of the company information (materials) on issues within the competence of the boiler house.

4.19. Check the readings of the devices that record the results of the production activities of the boiler house and located on the territory of the structural divisions of the enterprise.

4.20. Conduct negotiations with outside organizations within its competence in accordance with the established procedure, and sign agreements.

4.21. Use the funds allocated to finance the boiler house for the purchase of equipment, components, tools, repair equipment.

4.22. Make proposals on issues within the competence of the boiler house.

5. INTERACTION WITH THE STRUCTURAL DIVISIONS OF THE ENTERPRISE

5.1. In the process of production activity, the boiler plant cooperates with the following structural subdivisions:

- ______________________________________________________________,

- ______________________________________________________________,

- ______________________________________________________________.

6. RESPONSIBILITY

6.1. All responsibility for the quality and timeliness of the performance of the tasks and functions assigned to these Boilers is borne by the Head of the boiler house.

6.2. Responsibility of the boiler house workers is established by the current legislation and job descriptions.

6.3. The head and other employees of the boiler house are personally responsible for the compliance of the documents and correspondent transactions with the legislation of the Russian Federation with them.

7. CRITERIA FOR ESTIMATION OF THE ACTIVITY OF BOILER

7.1. Timely and high-quality implementation of set goals and objectives.

7.2. Qualitative performance of functional duties.

Head of the Boiler Room: ____________________________ / ________________ / / (signature) (Full name)

Obligations of the boiler room attendants. The procedure for allowing individuals to service boilers. The service of boilers may be allowed to persons who have reached the age of 18, who have undergone a medical examination, trained in the relevant program and have a certificate of the qualification commission for the right to service the boiler. Certification of boiler drivers is carried out in the permanent qualification commissions organized at specialized vocational schools, training centers and other educational institutions. Certification is also allowed at enterprises and organizations that have the necessary conditions and specialists, in consultation with local organizations of the Gosgortechnadzor. Participation of a representative of the local body of Gosgortechnadzor in the work of the qualification commission for the certification of boiler drivers is compulsory. The local authority of the Gosgortechnadzor is notified of the day of examinations for 10 days.

Re-examination of the knowledge of the boiler-house attendants is carried out annually, as well as when switching to another enterprise and in case of switching to the maintenance of other types of boilers or transferring the boilers from solid fuel to liquid ones in commissions directly at enterprises or organizations without the participation of a representative of the local Gosgortechnadzor. When transferring personnel for the maintenance of boilers operating on gaseous fuels, the knowledge test is carried out in the order, established by the rules  safety in the gas economy.

Organization of work on boiler plant maintenance. Service personnel are responsible for the condition of the boiler, equipment, fittings, instrumentation and for compliance with the rules, safety regulations, the violation of which can lead to a boiler accident, often accompanied by large disruptions and accidents.
For reliable and economical operation of the boiler house equipment, it is necessary to maintain the appropriate technical documentation: the technical passport of the boiler in the established form, the logbook and repair magazine, the book of instructions for the boiler room, the log of inspection and equipment defects and daily subscriptions. The technical passport must have all the data about the boiler: the address of the boiler installation, its name and type, the heat output, the heating surface, the permissible pressure, the name of the manufacturer, the year of manufacture, the date of commissioning the boiler, the metal grade from which the boiler is made.

In the logbook they record orders about the time of starting and stopping the equipment, describe the accidents and malfunctions in the operation of the equipment, indicating the causes and ways to eliminate them. When taking and passing shifts in the log make an appropriate entry. In the repair magazine, which records the repairs performed on the boilers, records should be kept of the acceptance of the boiler after repair.

In the book of orders, current orders are noted, as well as orders not provided for by instructions. In the log of inspections and defects of equipment record the results of inspection and testing of equipment as well as all defects detected by the attendants during the watch. The daily records record the parameters and operation modes of the boilers according to the testimony of the instrumentation.

Obligations of the boiler room attendants. Responsibilities of the boiler operator. The driver must remember his rights and duties, clearly know to whom he is subordinate, whose orders he must execute, who to report on accidents and malfunctions, about fire and accidents. The operator of the boiler room must serve the water and steam boilers, working on solid, gaseous and liquid fuels; inspect boilers and auxiliary equipment; to accept and hand over shifts to keep journals; to test and start up boilers and auxiliary equipment; melt the boiler on solid, gaseous and liquid fuel, switch it on and stop in accordance with the current instruction; correctly conduct the furnace mode, timely feed boilers and heating system and feed steam boilers; to observe the instruments, and also visually after the furnace process and heating the water in the boilers in accordance with the heating schedule, clean the furnace and the heating surfaces of the boiler from slag, ash and soot; clean the boiler of scale and rinse it, minor repairs equipment (stuffing stuffing boxes, replacing gaskets, etc.); service central water heating systems (fill, drain, feed, flush and remove air), and also serve the air heating and hot water supply systems of individual and group boilers; prepare solid fuels for combustion (sorting, crushing), to load fuel into the furnace of the boiler and perform its shuffling; to prevent possible accidents, and in case of their occurrence, to take prompt measures to eliminate them; be able to read the drawings and diagrams for the main and auxiliary equipment of heating boiler houses of low power; observe the safety rules, as well as hot water and steam boilers with excessive pressure »Gosgortekhnadzor 1 USSR and instructions for servicing boiler room equipment from using fire protection means. The boiler house operator should know the rules for the arrangement and maintenance of hot-water and steam boilers and the combustion appliances used in them, burners, injectors and auxiliary mechanisms; characteristic of the main types of fuel and ways of rational combustion of these in boiler furnaces; applied methods for cleaning boilers from scale and their washing, as well as cleaning the boilers of ash and soot; Applicable methods of water treatment of heating boilers of low power; device and maintenance of pipeline systems for water and steam supply of the water and steam heating  and hot water supply, as well as feed and make-up water, gaseous and liquid fuels; the device and maintenance of air heating systems, blowing fans, smoke exhausters, circulating, nutrient and sub-pump pumps; purpose, device and maintenance rules of the applied control and measuring devices of safety control automatics systems; properties and areas of application of thermal insulation; along with keeping records in the logbooks of other journals; rules of safety techniques and rules of the Gosgortechnadzor of the USSR for the safe operation of hot-water and steam boilers of steam and hot water  safety in the gas economy, as well as internal regulations, production instructions, fire prevention measures and sanitary regulations; the fundamentals of the economy of labor and production.

Obligations of the boiler room attendants. The order of acceptance and delivery of the shift. Entry of the boiler room personnel for on-call duty and departure from duty must be carried out in compliance with the requirements of the Internal Regulations. In case of detection of malfunctions in the work of the equipment, the driver who takes over the shift must stay until the defects are eliminated, and the driver who takes the shift is obliged to notify the person responsible for the boiler room and act further on his instructions. Having convinced of the complete serviceability of all equipment. the driver must sign in the logbook. The driver taking the change must remember that he is responsible for the malfunctions and unsatisfactory condition of the equipment that occurred in the previous shift and not marked with a log on acceptance. It is not allowed to take or hand over a shift during an accident in the boiler room.

Engineers on duty are forbidden to perform any duties during the operation of the boiler, not directly related to the care of boilers or auxiliary equipment of the boiler house (for example, repairs can not be carried out, etc.). The workplace of the driver must be well lit; especially well should be illuminated by watermarking glasses, manometer and thermometers. When operating on gaseous fuels, the boiler room is additionally equipped with explosion-proof lighting with switches installed outside the entrance. Cleanliness and order should be maintained in the boiler room. The room should not be obstructed by foreign objects and fuel. The passages in the boiler room and the exits must always be free, the exit doors easily open outwards. In boiler houses operating on gaseous fuels, it is necessary to provide a three-time air exchange with the suction of air from the upper zone of the boiler house.